• 15 April 2005, 4:00 pm Friday, ready for forming Saturday morning! Red line = face of wall!
  • Same day, other side of building
  • New safety fencing installed!
  • Site conditions 20 January 2005
  • Site conditions 02 February 2005
  • Start of excavation 02 February 2005
  • Removal of the first 1,700 yards 02 February 2005
  • 02 February, view from above
  • Note the amount of dirt against the building, 02 February 2005
  • Thursday 03 February 2005 Bharati comes to the site!
  • 08 February 2005 note the amount of cut at the top of the embankment
  • 09 February 2005 the view along the top of the embankment
  • 15 February 2005 excavation of 1,700 yds continues on the East side
  • 15 February 2005 a view from up the street, more trucking
  • 16 February 2005 almost around the building, almost! Retaining wall cut!
  • 10 March 2005 Excavation for water line completed
  • 10 March 2005, One dead oil tank!
  • 10 March 2005, Excavation for water main, note the ground water!
  • 24 March 2005, Cold, wet, mudy and the chiminy is down, however not removed
  • Chiminey down! 24 March 2005
  • 11 April 2005, Michael's stuff gone, excavation work continues
  • 13 April 2005, Water, Water everywhere, not to mention mud, lots of mud
  • 14 April 2005, More water issues, site visit by engineer!
  • 14 April 2005, New dry well, deeper dry well!
1 2 3 4 5 next